Work at Bambach’s new Rosedale plant in country Victoria is rapidly progressing with a number of machines now installed.
Power infrastructure is scheduled for completion by 15 May and initial commissioning of the first full production line to be installed will occur immediately thereafter. The first line will be capable of manufacturing Advance branded Air Conditioning Cable, Advance Polyfoam cables and basic TPS.
Further lines are also under installation with the factory scheduled to be in full production by the start of the new financial year.
Over the past three months the factory has been completely renovated with large concrete structures demolished, new roofing installed, new lighting, complete refurbishment of the extensive offices and substantial concrete repair of the factory floor. Whilst a lot remains to be done the project is on track and now on the “downhill” run.